PROJECT DETAILS
CLIENT: Confidential Client
LOCATION: Morrisville, NC
DESCRIPTION:
The Perimeter 2 Decommission project consisted of removal of owner equipment from an existing facility in Morrisville, NC. The client was moving their operations to a new facility and were required to remove various items such as (4) roof top units, (2) split systems, (2) humidifiers, server room electrical infrastructure, UPS removal, and removal of a pre-action system and installation of a new wet sprinkler system. Most notably, the client requested the removal of a 550kW generator and relocation to their new site in Holly Springs. Eno Company facilitated the logistics of the crane operations and transportation and coordinated with the project team in Holly Springs to ensure a successful delivery